针对资料处理中心的空调解决方案,资料处理中心的特点为服务器处理资料的场所,资料处理中心有大量发热设备,资料处理中心内人员不会太多。根据资料处理中心的特点,空调选型推荐如下:HIMOD P16机型。
This is a solution of A/C for a data processing center. The characteristic of the data processing center is the place where the server processes the digital data, and there is a large amount of equipment. Personnel are not too much. According to the characteristics of the space for the data processing center, the selection of model is recommended as HIMOD P16.
经济效益评估:(Economic Evaluation)
  • 该资料处理中心需安装空调面积总计200平方米左右,有大量发热设备,对温湿控制及节能有较高的要求,依据实际情况每平米所需制冷量平均按500W计算,总需求100KW制冷量。
The total area is of about 200 square meters for the data processing center, and there is a large amount of heat source, and it highly requires the temperature and humidity control and energy saving features. Required cooling capacity per square meter on average calculated based on the actual situation according to 500W, the total demand for cooling capacity is of 100KW.
  • 要满足该项目100KW的制冷量,需使用HIMOD P16机组2套装机。
To meet the cooling capacity of 100KW, this project is needed to use two sets of units (HIMOD P16).
  • 经济效益对比估算:传统空调满足100KW制冷量的输入功率至少为39.5KW左右,而HIMOD P16机组1套主机的输入功率合计为12.84KW,主机部分省电35%,全年共计节省电费2.6万元以上。(按1年运行8个月,1月运行30天,1天运行8小时,用电按1元1度计算)
Comparison of economic benefit estimation: the traditional air-conditioning input power (100KW cooling capacity) is at least about 39.5KW, and the HIMOD P16 input power per set is of 12.84KW. The energy saving is up to 35%. The annual saving is more than 26000 CNY. (According to 8 months per year, 30 days per month, 8 hours per day of operation, electricity by 1 CNY/1 degree calculation)